We are still working on migrating to the new Bosch Connected Industry Online Portal. Stay tuned! Click here for the latest updates.
06-15-2022 02:05 AM - last edited on 06-15-2022 09:25 AM by nexidator
Hello, good afternoon
I interested in updating our software from OES 4.10 to OES 4.11, we are interested in knowing the process to carry out said update.
06-15-2022 09:30 AM
As always when updating a project from to a newer OES or CpStudio version, the first step is to open the new OES version. Using Project --> Open, select the existing project. OES 4.11 will ask whether you want to convert the project. Next, you will be asked to provide an ORD file for the HMI modulo. It is always necessary to use an HMI version that matches the OES version. In your case, you should use the latest HMI modulo V4.11 version (but any 4.11.x version will work).
As OES 4.10 and 4.11 are very similar (except for added features), that's all you need to do.
After updating the project, just run the export and deploy the HMI including the Standard files.
06-15-2022 03:23 PM
Thanks for the information, but what I am looking for is to pass the OES V4.10 software to V4.11. Do not update a project, what would be the process at the software level to have the new version?
06-16-2022 10:02 AM
I am not sure if I understand your question correctly, but you cannot update OES4.10 software to OES4.11. These are absolute independent versions, so you can use both of them simultaneously.
For example on my PC I installed all versions of OES from version 4.7 to 4.11. OES project contains information about version in which was created, so if you use doubleclick at *.oep file in Engeneering folder, it always opens correct version of OES.